Expediting Generator Interconnection Procedures Act of 2025

USA119th CongressHR-2986| House 
| Updated: 6/24/2026
Kathy Castor

Kathy Castor

Democratic Representative

Florida

Cosponsors (1)
Mike Quigley (Democratic)

Energy Subcommittee, Energy and Commerce Committee

  • Introduced
  • In Committee
  • On Floor
  • Passed Chamber
  • Enacted
This legislation directs the Federal Energy Regulatory Commission (FERC) to undertake a rulemaking process within 180 days of its enactment. The primary goal is to address existing inefficiencies in procedures for connecting new electric generation and energy storage projects to the transmission system , ensuring they can interconnect quickly, cost-effectively, and reliably. This involves revising the pro forma Large Generator Interconnection Procedures and Agreements to streamline the process and improve interconnection procedures . Specifically, the bill requires transmission providers to develop and employ modeling assumptions based on actual operating abilities, study interconnection requests consistent with customer risk tolerance, and select cost-effective solutions for network reliability needs. They must also provide transparent information to interconnection customers, utilize queue management best practices like advanced computing and automation, and implement measures to ensure timely and cost-conscious construction of necessary network upgrades . FERC is mandated to issue a final rule within 18 months, though the bill explicitly states it does not alter FERC's existing cost allocation authority.
View Full Text

Suggested Questions

Get AI-generated questions to help you understand this bill better

Timeline

Bill from Previous Congress

HR 118-8085
Expediting Generator Interconnection Procedures Act of 2024
Apr 24, 2025
Introduced in House
Apr 24, 2025
Referred to the House Committee on Energy and Commerce.
Apr 24, 2026
Referred to the Subcommittee on Energy.
Jun 24, 2026
Forwarded by Subcommittee to Full Committee (Amended) by Voice Vote.
Jun 24, 2026
Subcommittee Consideration and Mark-up Session Held
  • Bill from Previous Congress

    HR 118-8085
    Expediting Generator Interconnection Procedures Act of 2024


  • April 24, 2025
    Introduced in House


  • April 24, 2025
    Referred to the House Committee on Energy and Commerce.


  • April 24, 2026
    Referred to the Subcommittee on Energy.


  • June 24, 2026
    Forwarded by Subcommittee to Full Committee (Amended) by Voice Vote.


  • June 24, 2026
    Subcommittee Consideration and Mark-up Session Held

Energy

Electric power generation and transmissionEnergy efficiency and conservationEnergy storage, supplies, demandInfrastructure developmentPublic utilities and utility rates

Expediting Generator Interconnection Procedures Act of 2025

USA119th CongressHR-2986| House 
| Updated: 6/24/2026
This legislation directs the Federal Energy Regulatory Commission (FERC) to undertake a rulemaking process within 180 days of its enactment. The primary goal is to address existing inefficiencies in procedures for connecting new electric generation and energy storage projects to the transmission system , ensuring they can interconnect quickly, cost-effectively, and reliably. This involves revising the pro forma Large Generator Interconnection Procedures and Agreements to streamline the process and improve interconnection procedures . Specifically, the bill requires transmission providers to develop and employ modeling assumptions based on actual operating abilities, study interconnection requests consistent with customer risk tolerance, and select cost-effective solutions for network reliability needs. They must also provide transparent information to interconnection customers, utilize queue management best practices like advanced computing and automation, and implement measures to ensure timely and cost-conscious construction of necessary network upgrades . FERC is mandated to issue a final rule within 18 months, though the bill explicitly states it does not alter FERC's existing cost allocation authority.
View Full Text

Suggested Questions

Get AI-generated questions to help you understand this bill better

Timeline

Bill from Previous Congress

HR 118-8085
Expediting Generator Interconnection Procedures Act of 2024
Apr 24, 2025
Introduced in House
Apr 24, 2025
Referred to the House Committee on Energy and Commerce.
Apr 24, 2026
Referred to the Subcommittee on Energy.
Jun 24, 2026
Forwarded by Subcommittee to Full Committee (Amended) by Voice Vote.
Jun 24, 2026
Subcommittee Consideration and Mark-up Session Held
  • Bill from Previous Congress

    HR 118-8085
    Expediting Generator Interconnection Procedures Act of 2024


  • April 24, 2025
    Introduced in House


  • April 24, 2025
    Referred to the House Committee on Energy and Commerce.


  • April 24, 2026
    Referred to the Subcommittee on Energy.


  • June 24, 2026
    Forwarded by Subcommittee to Full Committee (Amended) by Voice Vote.


  • June 24, 2026
    Subcommittee Consideration and Mark-up Session Held
Kathy Castor

Kathy Castor

Democratic Representative

Florida

Cosponsors (1)
Mike Quigley (Democratic)

Energy Subcommittee, Energy and Commerce Committee

Energy

  • Introduced
  • In Committee
  • On Floor
  • Passed Chamber
  • Enacted
Electric power generation and transmissionEnergy efficiency and conservationEnergy storage, supplies, demandInfrastructure developmentPublic utilities and utility rates